CASE STUDIES
Hunter Water Corp. – Honeysuckle
- February 27, 2021
Project Overview
Solar Panels
224 x Sunpower E20 Series 327W (20% efficiency)
Inverters
4 x SMA STP17000TL
Est Annual Energy Generation
101.83MWh
Est CO2 Avoided Annually
109.3 Tonnes
Estimated Annual Energy Cost Savings
$15,300

Solar System Details
73.25 kW Grid Connect Solar System installed on the roof of Hunter Water’s head office above Newcastle Harbour. System has been installed over 3 roofs using Clenergy Tilt Framing.
Solar Panels
224 x Sunpower E20 Series 327W (20% efficiency)
Inverters
4 x SMA STP17000TL
Est Annual Energy Generation
101.83MWh
Est CO2 Avoided Annually
109.3 Tonnes
Estimated Annual Energy Cost Savings
$15,300
Project Challenges
Installation located on multi-storey building; working hours – after hours; working within Hunter Water guidelines